The stacker is one of the most important equipment in the automated warehouse, so for the installation of stacker equipment, we must take it seriously, to install in place, in order to maximize its role, so as to serve the automated warehouse.So what should we pay attention to when installing the stacker? Let’s share it with jujumi.
During the installation of the stacker, we need to pay attention to the following items:
(1) A certain installation space should be reserved. If this work is not done well in the early stage, the stacker will be installed when the shelf is half installed, and then the goods will be installed.
(2) When it is connected with the beam by hemp rope, it shall be fixed with Jack to prevent the beam from toppling.
(3) When using bolts to connect, it is necessary to use spanner to fasten and tighten, and the torque should be determined according to the drawing.After fastening, measure and record all kinds of data.
For stacker, there are two ways to install it on site
Integral hoisting: first assemble the upper and lower beams and columns together, then lift the stacker by 910 degrees and then lift it into the roadway.
Split lifting: use lifting tools to lift the column, and then connect the column with the lower beam by bolts through the walking mechanism.Fix the loading platform, lift the column, connect with the lower beam, and finally connect the upper beam with the column.